The right order of works in a renovation — and why it matters

The correct sequence: strip-out, services, plaster and screed, drywall, tiling, paint, flooring, furniture. Why each step comes where it does.

· Demgirişim

The backbone of a renovation is its order of works. Each job sits on top of the one before it; when the order breaks, finished work has to be redone. This article sets out the correct sequence and the reasoning behind each step.

The sequence and the reasons

OrderWorkWhy here?
1Strip-out and debris removalMeasurements and plans are not final until every layer is cleared
2Demolishing / building wallsService routes are set by the walls
3Electrical and plumbingBuried in walls; must finish before plaster
4Service testingDetecting leaks and faults before closing up
5Plaster and screedCovers services, gives flat surfaces and a level floor
6Wet area waterproofingBeneath tiles, after the screed has dried
7DrywallSuspended ceilings and coves; ceiling wiring must be in place
8TilingBathroom and kitchen walls and floors
9Satin gypsum and paintDust-producing work is finished; surfaces are ready
10Floor coveringPaint done, screed dry; parquet or vinyl laid
11Internal doors and joineryDoor undercut is set by the floor build-up
12Furniture installationPaint and floors ready; furniture is not damaged
13WorktopMeasured after units are installed
14Sanitaryware, taps, light fittingsFinal fixings
15Touch-ups, silicone, cleaningFinal check before handover

What happens when the order breaks

  • Adding electrics after painting: the wall is chased, then plaster and paint are repeated.
  • Parquet before the screed dries: the floor blisters, is lifted and relaid.
  • No ceiling lighting plan before drywall: the ceiling is cut open, jointing and paint repeated.
  • Drywall after flooring: the floor collects dust and scratches; protection and cleaning cost more.
  • Painting after furniture: units cannot be painted around cleanly; touch-up quality drops.

Work that can run in parallel

Some jobs need not wait for others: unit production continues in the workshop while plaster and screed proceed on site; metalwork fabrication runs alongside painting. A good schedule uses these parallels to shorten the overall programme.

Curing and waiting times

Plaster, screed, waterproofing and tile adhesive all need time to cure. These waits are a natural part of the calendar; skipping them costs quality. When waiting days appear in a work schedule, it is a sign the plan is realistic.

Who keeps track of the order?

In the model where trades are hired separately, the homeowner tracks the sequence and the trades wait on each other. Under a single-responsibility team, sequence and coordination sit with the contractor. See also apartment renovation step by step and the most common renovation mistakes.

Demgirişim plans the order of works on a day-by-day schedule and delivers every item with a single team in renovation and repair projects.

Frequently asked questions

Paint first or flooring first?

Paint first, then flooring. After the floor is laid, only the skirting line and touch-ups are painted. The other way round means protecting the new floor and cleaning paint splashes.

Does drywall come before or after painting?

Before. Once drywall jointing and filling are complete, satin gypsum and paint follow.

When are kitchen units installed?

After paint and flooring are finished. The worktop is measured after the units are fitted, so it arrives last.